PROJECTS FY 2021-2022
Totals and Funds Summary 2021-2022
Projects Per Department
| Department | Completed | Ongoing | Stalled | Not started | Inprocurement | All Projects | Total Budget |
|---|---|---|---|---|---|---|---|
| AGRICULTURE AND IRRIGATION | 29 | 0 | 0 | 0 | 0 | 29 | Ksh 486,578,020 |
| County Assembly | 1 | 0 | 1 | 0 | 0 | 2 | Ksh 32,434,033 |
| CPSM, ICT and Decentralized Units | 13 | 1 | 0 | 0 | 0 | 14 | Ksh 228,475,445 |
| Education and Technical Training | 270 | 18 | 1 | 0 | 0 | 289 | Ksh 239,064,773 |
| FINANCE AND ECONOMIC PLANNING | 8 | 0 | 0 | 0 | 0 | 8 | Ksh 138,904,345 |
| HEALTH AND SANITATION | 126 | 31 | 0 | 0 | 0 | 157 | Ksh 264,472,318 |
| Lands, Housing, Planning and Urban Development | 16 | 0 | 0 | 0 | 0 | 16 | Ksh 77,108,377 |
| Livestock, Fisheries and Veterinary Services | 72 | 3 | 0 | 0 | 0 | 75 | Ksh 235,386,648 |
| Public Works, Transport and Infrastructure | 194 | 0 | 0 | 0 | 0 | 194 | Ksh 403,669,807 |
| Tourism, Youths, Culture and Social Services | 24 | 0 | 0 | 0 | 0 | 24 | Ksh 81,050,367 |
| Trade, Industrialization and Cooperative Development | 3 | 0 | 0 | 0 | 0 | 3 | Ksh 5,517,042 |
| TRADE, INDUSTRIALIZATION, COOPERATIVE DEVELOPMENT | 36 | 4 | 0 | 0 | 0 | 40 | Ksh 61,695,442 |
| Water, Environment and Natural Resources | 183 | 1 | 1 | 0 | 0 | 185 | Ksh 355,763,606 |
| Total | 975 | 58 | 3 | 0 | 0 | 1036 | Ksh 2,610,120,223 |
Projects Per Subcounty
| Subcounty | Completed | Ongoing | Stalled | Not started | Inprocurement | All Projects | Total Budget |
|---|---|---|---|---|---|---|---|
| Central Pokot | 158 | 6 | 1 | 0 | 0 | 165 | Ksh 226,965,347 |
| Kacheliba | 134 | 6 | 0 | 0 | 0 | 140 | Ksh 202,184,964 |
| Kipkomo | 96 | 9 | 0 | 0 | 0 | 105 | Ksh 149,436,151 |
| NORTH POKOT | 136 | 9 | 0 | 0 | 0 | 145 | Ksh 178,615,140 |
| South Pokot | 105 | 11 | 0 | 0 | 0 | 116 | Ksh 138,879,079 |
| West Pokot | 346 | 17 | 2 | 0 | 0 | 365 | Ksh 1,714,039,541 |
| Total | 975 | 58 | 3 | 0 | 0 | 1036 | Ksh 2,610,120,223 |
Projects Per Ward
| Ward | Completed | Ongoing | Stalled | Not started | Inprocurement | All Projects | Total Budget |
|---|---|---|---|---|---|---|---|
| ALALE | 57 | 4 | 0 | 0 | 0 | 61 | Ksh 64,317,762 |
| ALL WARDS | 3 | 0 | 0 | 0 | 0 | 3 | Ksh 64,554,400 |
| Batei | 29 | 4 | 0 | 0 | 0 | 33 | Ksh 52,037,456 |
| Chepareria | 66 | 5 | 0 | 0 | 0 | 71 | Ksh 95,849,297 |
| CHEPARERIA AND WEI WEI | 1 | 0 | 0 | 0 | 0 | 1 | Ksh 1,549,398 |
| Endugh | 37 | 3 | 0 | 0 | 0 | 40 | Ksh 53,973,619 |
| KAPCHOK | 48 | 3 | 0 | 0 | 0 | 51 | Ksh 60,887,984 |
| Kapenguria | 103 | 5 | 2 | 0 | 0 | 110 | Ksh 949,672,339 |
| KASEI | 43 | 2 | 0 | 0 | 0 | 45 | Ksh 59,968,450 |
| KIWAWA | 36 | 3 | 0 | 0 | 0 | 39 | Ksh 54,328,928 |
| Kodich | 38 | 1 | 0 | 0 | 0 | 39 | Ksh 60,460,533 |
| Lelan | 57 | 9 | 0 | 0 | 0 | 66 | Ksh 80,979,326 |
| LOMUT | 41 | 4 | 1 | 0 | 0 | 46 | Ksh 63,493,642 |
| Masol | 39 | 0 | 0 | 0 | 0 | 39 | Ksh 59,495,188 |
| Mnagei | 48 | 2 | 0 | 0 | 0 | 50 | Ksh 104,792,163 |
| RIWO | 54 | 3 | 0 | 0 | 0 | 57 | Ksh 82,650,551 |
| SCHOOL | 2 | 0 | 0 | 0 | 0 | 2 | Ksh 1,499,525 |
| SEKERR | 44 | 1 | 0 | 0 | 0 | 45 | Ksh 48,204,935 |
| SIYOI | 55 | 0 | 0 | 0 | 0 | 55 | Ksh 47,350,757 |
| SIYOI, SOOK, ENOUGH,LOMUT, ALALE AND SEKER | 1 | 0 | 0 | 0 | 0 | 1 | Ksh 353,574,020 |
| SOME WARDS | 1 | 0 | 0 | 0 | 0 | 1 | Ksh 4,000,000 |
| Sook | 41 | 4 | 0 | 0 | 0 | 45 | Ksh 46,377,250 |
| SUAM | 48 | 2 | 0 | 0 | 0 | 50 | Ksh 80,836,447 |
| Tapach | 48 | 2 | 0 | 0 | 0 | 50 | Ksh 57,899,753 |
| VARIOUS WARDS | 1 | 0 | 0 | 0 | 0 | 1 | Ksh 5,594,917 |
| WEIWEI | 34 | 1 | 0 | 0 | 0 | 35 | Ksh 55,771,582 |
| Total | 975 | 58 | 3 | 0 | 0 | 1036 | Ksh 2,610,120,223 |